ruostela's blog
DanceNavigator: Week 20
Now we have only one week left for our project. And we don't have the licenses (suprise suprise). So we decided to go with the plan B. The target of plan B is to create some material that promotes our project and the targets we are trying to achieve with this project. We are going to make somekind of a promoting video, that presents the meaning of the program.
DanceNavigator: Two weeks left!
Now I'm really getting frustrated. We still have no information about when the licenses will arrive. And now we have only two weeks left before the deadline. We still haven't been able to test the program because we don't have the testing licenses. It's really frustrating as the progress of our project is not in our hands.
DanceNavigator: Week 10
This week we got some really bad news for our project: our lead programmer has to leave the project because he got some actual job. Due to this he doesn’t have time for the project anymore.
DanceNavigator: Week 9
As I said in my last blog entry, from now on the language will be English.
This week we had a meeting with our client. There were also four new team members (I only knew that there were going to be two), so I was a little bit confused. (Actually later that week two of our new members decided not to participate in our project.) In the meeting we went through what we've been doing these weeks and what we're going to in the next weeks.
DanceNavigator: Viikko 8
Tällä viikolla pohdimme edelleen ohjelman toiminnallisuutta ja sitä, mitä tässä vaiheessa kannattaa tehdä kun aikaa on n. 3 kuukautta ja ohjelman laajennusmahdollisuudet lähes rajattomat. Joudumme todennäköisesti rajaamaan muutamia ideoita pois ja tekemään tässä vaiheessa melko tiiviin paketin.